ISO 27001 Annex A 5.30 ICT readiness for business continuity
What it says
ICT readiness shall be planned, implemented, maintained and tested based on business continuity objectives and ICT continuity requirements.
Quoted as published. Everything else on this page is written by Control Stack.
In plain English
Plan, implement, maintain and test ICT readiness, based on your business continuity objectives and ICT continuity requirements.
Your organisation must plan, implement, maintain and test ICT readiness, based on its business continuity objectives and ICT continuity requirements. ICT readiness means your information and communications technology can keep running or be restored in time during a disruption. A business impact analysis (how long each activity can be down) usually sets the requirements, including:
- Recovery time objective (RTO): how quickly a service must be back.
- Recovery point objective (RPO): how much recent data can be lost.
All four actions apply, so an untested plan falls short.
Free. Save your status, tasks and notes.
Why it matters
An untested restore or a failover nobody has run can take far longer than the business can tolerate, so recovery targets mean little on their own. Testing against the targets shows the shortfall while there is still time to fix it.
How to implement
Set ICT continuity requirements through a business impact analysis.
Start from your business continuity objectives or, if none exist, agree them with activity owners. Work out how long each activity can be down, prioritise on that, and note which ICT services each depends on. Give each service an RTO, an RPO and the performance and capacity it needs during disruption.
Choose a continuity option for each service.
Compare ways to keep running and to recover: backups (Annex A 8.13), redundancy (Annex A 8.14), a standby site or a manual workaround. Pick what can meet the RTO and RPO, then build it.
Compare bought services with your objectives.
Read each provider's recovery commitments and compare them with your RTO and RPO. Where they fall short and the contract cannot change, add your own measure, such as an independent backup or a manual fallback, or record who accepted the gap.
Write ICT continuity plans with restoration steps.
Give each prioritised service its RTO, RPO, step-by-step recovery procedure and who can invoke the plan. Note which people or providers hold the skills, and keep a copy reachable during an outage. Annex A 5.29 covers keeping security during the disruption.
Test recovery and measure the result.
Restore data, fail over a service or run a full exercise, on a schedule you set by criticality. Record actual recovery time and data loss against the RTO and RPO, fix each shortfall and re-test. Update the plans with what you learn.
Keep it running
Set the test schedule by how critical each service is, because the control names no period. Update plans and re-test when a critical system, supplier or hosting arrangement changes, after a failed test or real outage, and when the business changes its recovery objectives.
Evidence and audit
- Check 1 of 5What an auditor asks for
Ask for
The list of prioritised ICT services with an RTO and RPO for each, and the business impact analysis behind them.
Look at
Whether every ICT service supporting a prioritised activity is included, compared with the service inventory, and whether the objectives trace to the analysis.
Good evidence
Every ICT service supporting a prioritised activity has an RTO and RPO that trace to the business impact analysis.
- Check 2 of 5What an auditor asks for
Ask for
The latest recovery test report for a sample of critical services.
Look at
Whether a real restore or failover was performed, and the measured time and data loss.
Good evidence
A real recovery met the RTO and RPO for each tested service, or each shortfall has an owner and a re-test date.
- Check 3 of 5What an auditor asks for
Ask for
Live backup and failover settings for a critical service.
Look at
The configured backup interval and failover setup, compared with the RPO and the plan.
Good evidence
The configured interval is no longer than the RPO, and any standby matches what the plan describes.
- Check 4 of 5What an auditor asks for
Ask for
The recovery commitments of a critical bought service, compared with your objectives.
Look at
Whether the provider's stated recovery times meet your RTO and RPO.
Good evidence
The commitments meet the RTO and RPO, or the gap has a working fallback or a recorded acceptance.
- Check 5 of 5What an auditor asks for
Ask for
Change records for critical systems since the last test.
Look at
Whether significant changes show up in the plans and were covered by a later test.
Good evidence
The plans name the systems now in use, and each significant change has been tested since it was made or has a test date set.
Mappings
Closest match in ASD Essential Eight: E8-RB-ML1.4, Test backup restoration to a common point during disaster recovery, which this control covers in full and more.
ASD Essential Eight: 2 mappings
This control is broader than E8-RB-ML1.4.
E8-RB-ML1.4 involves testing restoration from backups to a common point in time during disaster recovery exercises. Annex A 5.30 focuses on a broader ICT readiness for business continuity, including but not limited to backup restoration testing, stressing on overall continuity objectives.
This control partially meets E8-RB-ML1.1.
Annex A 5.30 requires ICT readiness to be planned, implemented, maintained and tested based on business continuity objectives and ICT continuity requirements. E8-RB-ML1.1 mandates that backups are performed and retained in line with business criticality and business continuity requirements, which is one specific control measure underpinning ICT continuity. E8-RB-ML1.1 is narrower (backup performance/retention) while Annex A 5.30 encompasses additional continuity design and readiness activities beyond backups.
ASD Information Security Manual: 13 mappings
This control is broader than ISM-0734.
ISM-0734 demands the CISO to assist in business continuity and disaster recovery planning to ensure business-critical services can be sustained in a disaster. ISO/IEC 27001:2022 Annex A 5.30 mandates planning, implementing, maintaining, and testing ICT readiness against continuity objectives, which is vital to effective DR planning. Annex A 5.30 is broader and more focused on ICT testing, while ISM-0734 emphasises the CISO's regulatory and oversight role across BC/DR planning.
This control is broader than ISM-1438.
ISM-1438 requires organisations with a high availability requirement for website hosting to use CDNs that cache websites to improve resilience and uptime. Annex A 5.30 requires ICT readiness for business continuity to be planned, implemented, maintained and tested against continuity objectives, which can include architectural measures like CDNs for web continuity. The ISO control is broader and programmatic (planning, maintenance, testing across ICT), while ISM-1438 is a specific technical pattern for website availability.
This control is broader than ISM-1548.
ISM-1548 requires organisations to develop, implement and maintain data restoration processes and supporting procedures. Annex A 5.30 supports ISM-1548 by requiring ICT readiness for business continuity be planned, maintained and tested, of which data restoration is a core capability.
This control is broader than ISM-1610.
ISM-1610 requires a method of emergency access to systems and resources to be documented and tested on initial implementation and after fundamental ICT infrastructure changes. Annex A 5.30 requires ICT continuity readiness, including testing against business continuity requirements. While A 5.30 is broader in scope, covering overall ICT continuity, ISM-1610 specifically targets emergency access procedures.
This control partially meets ISM-1019.
ISM-1019 requires a documented and maintained DoS response plan for video conferencing and IP telephony services. Annex A 5.30 focuses on ICT readiness for business continuity, covering broader continuity scenarios including DoS. ISM-1019 is narrower as it targets specific services and threats.
This control partially overlaps ISM-1431.
Annex A 5.30 requires organisations to plan, implement, maintain and test ICT continuity capabilities to support the business during disruptions. ISM-1431 relates by requiring denial-of-service (DoS) mitigation planning with cloud providers, supporting service availability during specific disruptions. The candidate is narrower, whereas Annex A 5.30 covers all ICT continuity requirements and broader business continuity objectives including recovery goals.
This control partially overlaps ISM-1511.
Annex A 5.30 requires ICT continuity requirements to be implemented based on business continuity objectives and then maintained and tested. ISM-1511 relates by requiring data backup, which is a key ICT continuity control. ISM-1511 is narrower (backup execution and retention), while Annex A 5.30 includes broader ICT readiness activities such as recovery strategies and continuity testing across services.
This control partially overlaps ISM-1547.
Annex A 5.30 requires ICT readiness for business continuity to be planned, implemented, maintained and tested against business continuity objectives and ICT continuity requirements. ISM-1547 involves documented and maintained data backup processes and procedures, which are a foundational ICT continuity capability, though Annex A 5.30 is broader, emphasising end-to-end ICT continuity readiness and testing.
- ISM-1580Automatic availability zone transition for high availability online servicesPartially overlaps
This control partially overlaps ISM-1580.
Annex A 5.30 requires organisations to ensure ICT services can continue or be recovered to meet business continuity objectives. ISM-1580 relates by requiring high availability online services to automatically transition between availability zones, supporting continuity during infrastructure or zone outages. The candidate is a specific pattern for availability, while Annex A 5.30 includes planning, maintenance, and testing for all relevant ICT services.
This control partially overlaps ISM-1805.
Annex A 5.30 requires planned, maintained, and tested ICT readiness to sustain or recover ICT services during disruptive events. ISM-1805 relates by detailing what a denial-of-service response plan must contain for maintaining video conferencing and IP telephony capabilities during an attack. The candidate is specific, whereas Annex A 5.30 is broader and covers all relevant ICT continuity requirements.
This control supports ISM-1123.
ISM-1123 requires UPS power to be used for all TOP SECRET IT equipment so services remain available during loss of mains power. This supports Annex A 5.30 because UPS-backed power is a common ICT continuity measure that contributes to ICT readiness for business continuity objectives. Annex A 5.30 includes planning, testing and broader continuity arrangements, whereas ISM-1123 is a single physical power-control requirement.
This control depends on ISM-1615.
ISM-1615 requires break glass accounts to be tested after their credentials are changed to confirm emergency access will still function when needed. This supports Annex A 5.30 by providing a concrete, repeatable test activity that evidences ICT continuity readiness for a critical recovery mechanism (emergency administrative access). Annex A 5.30 is broader and lifecycle-focused (plan, implement, maintain and test ICT continuity), while ISM-1615 focuses on post-change validation for one continuity-enabling control (break glass access).
This control depends on ISM-1633.
ISM-1633 requires defining system boundaries, criticality and security objectives based on impact if compromised. This supports ISO/IEC 27001:2022 Annex A 5.30 because ICT continuity objectives and readiness planning depend on understanding which systems are critical and what availability/recovery objectives are required. Annex A 5.30 focuses on continuity planning and testing, whereas ISM-1633 establishes the business-driven objectives that continuity requirements should reflect.
ASD Essentials for enterprise IT: 2 mappings
- IT.PRO-10.1Back up important data, applications and settings on schedule to protected storageBroader than
This control is broader than IT.PRO-10.1.
IT.PRO-10.1 requires important data, applications and settings to be backed up on a defined schedule to secure, resilient and protected storage. Reliable backups are a core component of the ICT readiness required by Annex A 5.30, because they make recovery in line with business continuity objectives and ICT continuity requirements possible. Annex A 5.30 is broader, requiring ICT readiness as a whole to be planned, implemented, maintained and tested, beyond the backup arrangements in IT.PRO-10.1.
- IT.PRO-10.3Regularly test backup and restoration procedures against defined recovery objectivesBroader than
This control is broader than IT.PRO-10.3.
IT.PRO-10.3 requires regular testing of backup and restoration procedures against defined recovery time and recovery point objectives. Restoration testing against these objectives is a specific part of the ICT readiness testing required by Annex A 5.30, which is driven by business continuity objectives and ICT continuity requirements. Annex A 5.30 is broader, covering the planning, implementation, maintenance and testing of all ICT readiness arrangements, not only backup restoration.
Mappings show how controls relate across frameworks. They do not imply full equivalence or certification.
Get help with this control